Evans Jones was contracted by the developer Robert Hitchins to oversee a multi-million-pound development comprising of approximately 20,000 ft of office space and the construction of a twin-deck car park for 172 vehicles.

  • Location:
  • Carterton
  • Value:
  • £4.2M

Evans Jones project management team liaised with both the developer, contractors, and the end client, AirTanker, to ensure current needs were accommodated as well as future expansion requirements.

The site was extremely tight, requiring specific constraints issues to be overcome. 

Evans Jones kept all key parties informed on progress through the project, considering design, quality, risk, financial and compliance issues. 

The Results:
Evans Jones planned, coordinated, controlled, and reported on all aspects of the project, from inception through to completion and beyond. All cost, time and quality targets were met, and the project went very smoothly throughout.